A convenience store posted the following figures for gasoline sales in gallons over the past 4 days compared to its forecasted sales using two different forecast methods.
Given the following information, calculate the critical ratios, and indicate which activities are on target and which need to be investigated. Comment on the situation for each of the activities.
Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. What is your overall interpretation
Draw the network. What is the critical path? How many weeks will it take to complete the project? Which activities have slack, and how much?
Develop a modified chase strategy where overtime and inventory can be used, but the approach is to minimize inventory levels. Assume there are currently 10 employees.
Mark works for Grasslands Surveyors, Inc. as a surveyor. As part of his job, Mark has to drive all over Texas measuring and surveying land for his company.
Molly has just graduated from college when her car breaks down. She needs to buy a new car quickly so she can get to and from her new job.
Does Brendan have an enforceable security interest? Explain in detail why or why not. How can Brendan let other creditors know of his interest in the necklace? Explain the process in detail.
Pick three of the eight-step change theory components and give an example for each step that explains how leaders can implement it to effect change.
Suppose that an increase in warehousing costs and other costs brings inventory carrying costs to $2 per unit per month. All other costs and quantities remain the same.
In your own words, define managerial epidemiology and address the significance of using epidemiology principles and tools while making administrative decisions.
Assuming that 10 observations are adequate for thesepurposes, determine the three-sigma control limits for defects per shirt.
An important part of a projext is to identify the key process input variables (KPIV) and key process output variables (KPOV). Suppose that you are in charge of a hospital emergency room.
Suppose that a project will generate $A per year. in savings or increased profit for a period of x years. The projected cost of project completion is $C.
Final decision will be yours and you make decision based on the expected value from each player. Create a decision tree and analyze the data.
What is his/her multi factor productivity with current paint and with new paint in Bats/dollar? What is the percent change in productivity from current to new paint?
Assume you have collected data on sales associates of a manufacturing organization in a major metropolitan area. You analyze the data by type of work classification, education level.
If a pilot test revealed 45% perceived poor service quality, and we decide the interval range is + 10 percent with a 95% confidence level, what is the calculated sample size to confirm or not the fi
Finco must determine how much investment and debt to undertake during the next year. Set up an LP whose solution will tell Finco how to maximize its NPV. Then Graphically solve the LP.
Give an example illustrating how each component can be used to improve the organization and job of the employee. (Consider your present or recent job to answer this question)
Discuss the concept of the ‘long tail' in relationship to Netflix's business model/strategy and how this concept has evolved with the company's transition to streaming video.
Examine whether the three approaches can be used independently or in combination with each other. Support your answer with examples.
Discuss the basics of Just-in-Time using an example from the industry. Further, justify whether Just-in-Time is an inventory control policy or a process improvement methodology.
Ensure that you tie the manufacture of the computer to the Supply Chain Operations Reference (SCOR) model's five basic processes: Plan, Source, Make, Deliver, and Return.
In ancient Chinese proverb says, "In addition to the noble art of getting things done, there is the noble art of leaving things undone. The wisdom of life consists in the elimination of the non-esse