Zhang Industries budgets production of 270 units in June and 280 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate if $13.40 per hour. The indirect labor rate is $20.40 per hour. Compute the budgeted direct labor cost for July. $8,262. $5,427. $8,568. $5,628. $14,196