Zellars, Inc. is considering a project B. Project B costs $120,000 and is expected to generate $64,000 in year one, $67,000 in year two, $56,000 in year three, and $45,000 in year four. Zellars, Inc.'s required rate of return (WACC) for these projects is 10%. The net present value for Project B is.