Your project had a cost overrun in the past and you tried to obtain funding on topof the original budget at completion (BAC). Management has told you that theycannot make additional funding available. You have to increase cost performanceso that the project will be finished with costs not exceeding the original BAC.Which metric describes the future performance to meet this objective?