Your organization has a policy that any project changes that increase the projects budget buy more than 2.5% must be signed off by the project office. You have a change that was requested by the customer that will increase the budget by 4%; however, the customer has offered to pay for all of this change and does not want to slow it down which option represents the best choice?
Approve the change
Ask the customer to take the change to the project office and explain the situation
Do not allow the change since it increases the budget beyond your organization’s threshold
Take the change to the project office