Question: Your firm is considering two projects with the following cash flows:

a. If the appropriate discount rate is 12%, rank the two projects.
b. Which project is preferred if you rank by IRR?
c. Calculate the crossover rate - the discount rate r in which the NPVs of both projects are equal.
d. Should you use NPV or IRR to choose between the two projects?