Your firm is considering a project with the following timeline and cash flows:
Year 0: -$3,000 Year 1: $850 Year 2: $980 Year 3: $1,010 Year 4: $1,200 Year 5: $1,450
If the appropriate cost of capital is 9 percent, what's the NPV statistic for the project, and should the firm accept or reject the project with the cash flows given?
A. -$1284.19; Reject B. -$1124.45; Accept C. $1,326.24; Reject D. $1,177.08; Accept