Your company bid this contract with the promise to complete


You conducted a Crystal Ball simulation with project completion times, as shown below:

1964_3caf28a3-1eb7-4863-9b45-eb6bdceec8fa.png

a. Your company bid this contract with the promise to complete the job within 185 days. What is the probability of completing this project in that time frame? (Show your work.)

b. Develop a chart that would be of interest using the information provided.

c. Explain your chart in simple terms.