Your boss has requested that you analyze two projects for


Your boss has requested that you analyze two projects for him and pick the one you would recommend for investment. Both projects have the same risk because they are in the same business, and their cash flows are: Project A (Year 0: -$100,000; Year 1: $30,000; Year 2: $40,000; Year 3: $50,000; Year 4: $100,410); ... Project B (Year 0: -100,000 Year 1: 0 year 2: 10,000 Year 3 10000 Year 4 225500