You have just performed a scenario analysis on a project, with the following results:
Best Case: with a 35% probability, you get an NPV of $77
Base Case: with a 55% probability, you get an NPV of $24
Worst Case: with a 10% probability, you get an NPV of -$-18 (yes, that's negative)
What is this projects Expected NPV?