You have created the project charter but could not get it


You have created the project charter, but could not get it approved. Your manager and his boss have asked that the project begins immediately. Which of the following is the BEST thing to do?

A. Set up an integrated change control process

B. Show your manager the impact of proceeding without approval

C. Focus on completing projects that have signed project charters

D. Start work on only the critical path activities