1. You have completed updating your project status in Microsoft Project and posted your completed file to your company's web server for everyone to access. Is this project communication? Why or why not?
2. Your earned value analysis calculates, "The PV was $240, the EV is $230, and the AC is $250, so we have a CV of $-20 and an SV of -$10." What does this information tell you about this project? What else might you need to know? Explain this as though you were presenting to someone who does not understand the earned value terminology.
3. What are the important elements of a project communication plan? Please identify these elements and briefly discuss their importance.