You have been assigned as the new Project Manager to a $20M, 3 year project that is 6 months behind schedule and $1M over budget after one year. Assuming this is a Firm-Fixed-Price contract: (a) What three key questions would you ask the previous project manager? (b) What would you tell the customer? Assuming this is a Cost Reimbursable contract (cost plus fixed fee): (a) What three key questions would you ask the previous project manager? (b) What would you tell the customer?