You have a project with the following cash flow stream (assume a 10% discount rate). What is the profitability index of the project? Is it acceptable?
Initial investment ($76,000)
Year 1 $20,000
Year 2 $20,000
Year 3 $20,000
Year 4 $22,000
Year 5 $32,000
Disinvestment ($4,000) at Year 5
Part A: Calculate the profitability index for this project
Part B: Is the project favorable? Why or why not?