You are the project manager of a team that has been asked to complete the design of a chemical plant up to the stage of design selection. You have three engineers available (plus yourself) and the work must be completed in ten weeks. Develop a project plan and schedule of tasks for each engineer. Be sure to allow sufficient time for equipment sizing, costing, and optimization. What intermediate deliverables would you specify to ensure that the project stays on track?