You are the project manager for your company, Mark Manufacturers. Your company has a large client that has requested a special component be created for one of their test engines. Your organization agrees and creates a standard contract with the customer, and your manager assigns you to manage this project. The project was launched because of which one of the following?
A. A customer request
B. A change in the technology your customer is creating
C. A legal requirement (contractual)
D. An organizational need