You are presented a proposal for a project. The project costs $10,000,000 and will produce after-tax cash flows of $$2,000,000 at the end of year 1, $4,000,000 at the end of year 2, and $8,000,000 at the end of year 3. What is the NPV of this project if your WACC is 15%?