You are considering the following two mutually exclusive projects. The required rate of return is 14.5% for project A and 13.7% for project B. Which project should you accept and why?
Year Project A Project B
0 - $50,000 - $50,000
1 + $25,000 + $41,000
2 + $36,000 + $20,000
3 + $21,000 + $10,000