You have been asked by a retail association to develop an inventory control program for use on a PC. The program development requires the completion of the following three activities in sequence. You are concerned about the likelihood of finishing the project in the promised 10 days.
![1346_d7757d18-9c0b-4405-b958-6e0c8d581eba.png](https://secure.tutorsglobe.com/CMSImages/1346_d7757d18-9c0b-4405-b958-6e0c8d581eba.png)
Using the Monte Carlo method, simulate 10 program development experiences. On the basis of your simulation results, what is the probability of finishing the project in 10 days?