You are calculating the estimated time to completion for a


Question: Suppose, for Problem, that your PV was 75 and your EV was 80. Recalculate the SPI and estimated time to completion for the project with this new data.

Problem: You are calculating the estimated time to completion for a project of 15 months' duration and a budgeted cost of $350,000. Assuming the following information, calculate the Schedule Performance Index and the estimated time to completion (figures are in thousands).

1547_SV.png

Request for Solution File

Ask an Expert for Answer!!
Operation Management: You are calculating the estimated time to completion for a
Reference No:- TGS02637020

Expected delivery within 24 Hours