You are analyzing the ability of your firm's process to meet customer specifications and have the following information:
Variance = 6.5
Upper Specification Limit 210
Lower Specification Limit 181
Upper Control Limit 186
Lower Control Limit 172
The Cp is:
Express with 2 decimals.
The answer is 1.9