You are analyzing a very low-risk project with an initial cost of €120000. The project is expected to return €40000 the first year, €50000 the second year and €60000 the third year. The current spot rate is €.54. The nominal return relevant to the project is 4 percent in the U.K. and 3 percent in the U.S. using the home currency approach, what is the net present value of this project in U.S dollars?