You have been asked to create a project plan to build a playground for children in your local community. Your project should have 10-15 tasks (therefore, your network will have 10-15 nodes).
Please perform the following for this project: Develop a WBS for your project.Hand-draw a network diagram for your project.Perform the forward and backward pass to calculate the slack for each task. Write a short narrative that describes your network’s overall sensitivity.