Work scheduling problems section 35 p76 5 each day workers


Work Scheduling Problems: Section 3.5 (p.76) #5: Each day, workers at the Gotham City Police Department work two 6-hour shifts chosen from 12 A.M. to 6 A.M., 6 A.M. to 12 P.M., 12 P.M. to 6 P.M., and 6 P.M. to 12 A.M. The following number of workers are needed during each shift: 12 A.M. to 6 A.M. - 15 workers; 6 A.M. to 12 P.M. - 5 workers; 12 P.M. to 6 P.M. - 12 workers; 6 P.M. to 12 A.M. - 6 workers. Workers whose two shifts are consecutive are paid $12 per hour; workers whose shifts are not consecutive are paid $18 per hour. Formulate an LP that can be used to minimize the cost of meeting the daily workforce demands of the Gotham City Police Department.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Work scheduling problems section 35 p76 5 each day workers
Reference No:- TGS01673152