Question: Using the following table of tasks:
a. Build using MSP an mpp file including a work breakdown structure and a Gantt chart showing the project critical path.
b. What does the critical path become if Task C takes three time units?
Task
|
Predecessor(s)
|
Time units required
|
A
|
None
|
1
|
B
|
A
|
2
|
C
|
A
|
1
|
D
|
B and C
|
1
|