Work breakdown structure and a gantt chart


Question: Using the following table of tasks:

a. Build using MSP an mpp file including a work breakdown structure and a Gantt chart showing the project critical path.

b. What does the critical path become if Task C takes three time units?

Task

Predecessor(s)

Time units required

A

None

1

B

A

2

C

A

1

D

B and C

1