With the following information in mind, a. construct the network diagram b. identify the paths and the critical one c. calculate slack d. and how long will it take to complete the project? Activity Duration Predecessor A 4 None B 6 A C 4 A D 2 C E 4 B F 5 B, D G 3 C H 4 F, G I 2 E, H