Wiley Coyote plans to invest in the "Catch RR" project. He expects the project to be a perpetually long project. His investment plan is shown in the table below.
At a 2% interest rate, how much money should Wiley Coyote set aside now in order to sustain this perpetual project?
Draw a CFD
|
Amount
|
Year incurred
|
Initial Cost
|
$300,000
|
Year 0
|
One time upgrade cost
|
$120,000
|
Year 15
|
Annual Operation and Maintenance
|
$1,500
|
Every year forever
|
Major Maintenance Costs
|
$10,000
|
First in year 10, then every 10 years
|