The MPS for product A calls for 100 units to be completed in week 4 and 200 units in week 7. Spare part demand for item B is 10 units per week. The bill of materials for product A is shown on the right, and the inventory records are shown below: Data category B C Lot sizing rule FQQ= 500 LFL Lead time 2 3 Beginning inventory 100 10 Scheduled receipts none 200A. Develop a material requirement plan for the next 7 weeks for items B and C. B. Will any action notices be generated? If so, explain what they are and why they must be generated.