Why stop the project before its planned completion


Question: If both parties agree to stop the project before its planned completion but cannot reach an agreement, which of these is NOT an appropriate action to take? a. Continue direct negotiations in an attempt to part amicably. b. Reach a settlement through legal resolution. c. Make sure everyone knows who is to blame for the failure to complete the project. d. Reach a settlement through alternative dispute resolution.

 

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Why stop the project before its planned completion
Reference No:- TGS03404205

Expected delivery within 24 Hours