Question: Project Manager should consider risks in a charter because: Question options: a) Risks that have negative impact on project objectives should be identified and addressed b) Risks that may have positive impact on project may create opportunities c) Risks that have positive impact on project objectives should be identified and capitalized upon d) All of these