Problem: A team will be working on a project with requirements that evolve over time. The stakeholders accept flexibility over predictability. The team values transparency and provides honest timeline and budget to their stakeholders. Which planning strategy should be applied to this scenario? Detailed release plan High level release plan No release plan Rolling wave release plan