Which one is the wip which one is the th and which one is


Degressive Insurance Company closes 15,000 claims per year, or on average 288 claims per week. The average claim-to-close time is 3 weeks. How many claims on average does Degressive have in process? (Hint: Think through the Little's law. Which one is the WIP, which one is the TH, and which one is the CT? What is the time unit we should use here?)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Which one is the wip which one is the th and which one is
Reference No:- TGS0920716

Expected delivery within 24 Hours