You have one supplier who is located in a country that experiences earthquakes and tsunamis. Which of the following would help mitigate the risk of that supplier going off line?
reinforce the building construction for the supplier
relocate the supplier to some other region in that country
buy and store as much material as possible when the supplier is on line