Which of the following statements is TRUE regarding critical paths?
The path that takes the shortest time to complete in a project is the critical path.
Some activities on the critical path may have positive slack time.
Some non-critical activities may have zero slack time.
For any project, the (expected) project completion time is equal to the (expected) time duration of the project’s critical path.