Which of the following statements concerning resource leveling is true?
Resource leveling will always increase project duration.
Resource leveling will never increase project duration.
Resource leveling may or may not extend the duration of a project, but can never reduce duration.
Resource leveling may increase, decrease, or leave unchanged project duration.