1. Which of the following statements are true regarding the scope baseline for a project?
The scope baseline is an output of the create WBS process.
The scope baseline is an output of the scope verification process
The scope baseline is an input of the create WBS process
The scope baseline is an input of the scope verification process
2. Which of the following statements regarding WBS are FALSE?
The WBS is deliverable-oriented grouping of project components that define the total scope of project
Each item in the WBS is assigned a unique identifier that can provide a means to track costs and resources
The WBS is used to show which work components have been assigned to which organizational units.
The WBS is an output of the Create WBS process