Which of the following is one of the roles of Intergrated Baseline Review (IBR) team members?
a. Government IBR team members provide the revised Intergrated Master Plan and Intergrated Master Schedule to the contractor PM.
b. Contractor IBR team members provide the revised Intergrated Master Plan and Integrated Master Schedule to the Government program manager.
c. IBR team member document the risks they identify in a project risk sumary
d. Government IBR team members train contractor IBR team members on the IBR process