Which of the following is NOT true regarding an in control process in which a measurement is above the upper control limit in a control chart (assuming control limits set at 3 sigma)? the process is now considered to be out of control there was a 0.3 percent chance of this situation occurring the process has two strikes remaining a root cause analysis should be performed