1. Which of the following choices is not one of the stages of a project life cycle?
A) Conceptualizing
B) Defining
C) Planning
D) Executing
E) Delivering
2. Elizabeth is deciding how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, the ______ organization would be the best choice.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
3. Which of the following is not true of multi-weighted scoring models?
A) Will include quantitative criteria
B) Will include qualitative criteria
C) Each criterion is assigned a weight
D) Projects with higher scores are considered more desirable
E) All of the above are true