Which of the following is NOT true concerning the difference between the project manager (PM) and the functional manager (FM)?
a) the PM is a facilitator the FM is a technical supervisor
b) the PM is a generalist the FM is a specialist
c) the PM must be able to integrate tasks; and FM must be able to analyze tasks
d) the PM uses an analytical approach the FM uses a systems approach
e) all of the above are true