1. Which of the following is not one of the six categories of cost presented in the textbook?
Price of Goods
Variable Manufacturing Costs
Fixed Manufacturing Costs
Semi Variable Costs
Total Production Costs
2. Which of the following statements about critical path scheduling is not true?
The critical path is the longest path through the network
Critical path scheduling allows managers to not manage non-critical activities
As a manager, we need to know the critical path to identify which activities we should focus our efforts on controlling
A delay in a critical path activity delays the expected project completion time
Critical path analysis lets us know which activities do not need to be managed as strictly.