Which of the following is a way to select cost drivers using monthly Earned Value Management (EVM) data?
Conduct extensive data validation checks on EVM data.
Conduct an Integrated Baseline Review (IBR) to better understand the risks in the performance measurement baseline (PMB).
Sort Work Breakdown Structure (WBS) elements by cumulative cost variances in dollars to determine those with the highest cost variances
Validate pricing data against market research