Which of the following inputs into MRP must have excellent data integrity for MRP to be effective?
I. Bill of Materials
II. Inventory information
III. Master Schedule
IV. Process routing precedence logic
a) I and II
b) II, III and IV
c) I, II, III
d) All are needed