1. A tracking Gantt chart does NOT allow for:
A. looking at today's activity progress and determining whether a single activity is behind schedule.
B. future projections of the project's status.
C. looking at today's activity progress and determining whether the entire project is behind schedule.
D. looking at today's activity progress and determining whether a single activity is ahead of schedule.
2. Which of the following forecasting methods uses executive judgment as its primary component for forecasting? ? Support your answer with a brief explanation.
A. Historical analogy
B. Time series analysis
C. Panel consensus
D. Market research
E. Linear regression