Which of the following describes Earned Value Management System (EVMS) surveillance
a. Scheduled audits by the Government of contractor compliance with accounting standards and EVMS guidelines.
b. An ongoing review process by which the Department of Defense (DoD) ensures a contractor's EVMS remains compliant with the EVMS guidelines.
c. A formal certification that a contractor’s written EVMS meets the 32 guidelines.
d. The series of accurate reports produced by a fully compliant EVMS.