1. Which of the following characteristics would make an activity an unattractive candidate for crashing?
a) It is in a bottleneck position
b) It has a long duration
c) Employees required to do the job have highly specialized skills
d) It is on the critical path
e) It is labor intensive and employees can be added easily
2. Critical chain considers resource availability when creating the WBS.
True
False
3. The Fishbone diagram, also known as Ishikawa diagram or cause-and-effect diagram is used to plan the project work to be done.
True
False