Which motorcycle should it produce


Harley Davidson sells motorcycle X and Y. Motorcycle X sells for $10,000, has variable cost (labor and material) of $2,000, and requires 10 hours of use of machinery to produce. Motorcycle Y sells for $12,000, has variable costs (labor and material) of $8,000, and requires 2 hours of machinery to produce. Harley Davidson has a capacity constraint of 5,000 hours of machinery use per year. Which motorcycle should it produce?