Problem: Today is day 4 on the production control calendar, and the three jobs shown are in welding. By least slack, which job has the lowest (least urgent) priority?
Job Operation lead time Operation Due Date
A 1 6
B 4 8
C 3 6
a) A
b) B
c) C
d) B and c are tied