1. Which estimating approach shows a tendency for the estimator to pad the task estimates?
Analogous
Parametric
Bottom-Up
Top Down
2. For Estimating purposes which of the following would provide an initial profile of project costs?
Budget
Definitive
Pro Forma
Contingency
Order of Magnitude