The following jobs are waiting to be processed at Rick carlson's machine center. Carlsons machine center has a reatively long backlog and sets fresh schedules every 2 weeks, which do not disturb earlier schedules. Below are the jobs recieived during the previous 2 weeks. They are to be ready to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contact numbers.
(Information table is first one attached on excel)
A) Complete the table below (its attached)
B) Which dispatching rule has the ebst score for flow time
C) Which dispatching rule has the best score for utilization?
D) Which dispatching rule has the best score for lateness?
E) Which dispatching rule would you select? Support you decision
Job Date Job Received Production Days Needed Date Job Due
CX-01 225 25 270
BR-02 228 15 300
DE-06 230 35 320
SY-11 231 30 310
RG-05 235 40 360